Permit expiration (180 days)
Published byTown of Mount Pleasant
Town FAQ: "Every permit issued shall become invalid (expired) unless the work authorized commences within 180 days after permit issuance or if there is a period of inactivity on a permit of 180 days. For permits not affected by the Building Permit Allocation Program, the Building Official is authorized to grant one or more extensions of 180 Days." Under BPAS the Town states permits not picked up and paid for within 180 days are voided and require reapplication; construction must commence within 180 days; and construction must be maintained in any rolling 180-day period.