Town of Mount Pleasant. Widened Park West Boulevard from two lanes to a four-lane divided section from the existing four-lane section near the Town recreation facility access road to the Bessemer roundabout, with bike lanes, a wider shared-use path, and improvements to the Queen's Gate roundabout. Schedule as published: design complete, permitting complete, construction complete April 2021. Cost estimate $9,690,708. Checked Sept 4, 2026.